PPAP – Production Part Approval Process (2024)

During the Start of Production (SoP) phase, each organization takes part in the Production Part Approval Process – PPAP.

It’s one of the stages of the delivered product approvals, apart from approving the production process and validating the manufactured product, which is supervised by the engineering department. The main goal of PPAP is:

  • actions and responsibilities defining to ensure correct application of the part approval process in the pre-launch phase and current production
  • verification that all Customer requirements have been fully understood by the Supplier
  • Verification that the off-Tool off Process (OTOP) will enable the production of parts compliant with these requirements.
  • verification of the passage of tests carried out for confirmation within the prescribed time,
  • verification that the final production process in the final location (OTOP) retains all functional, reliability, dimensional and aesthetic characteristics.

PPAP – Production Part Approval Process (1)

Sometimes is said that PPAP is a summary of our work as a supplier and is the culmination of Advanced Product Quality Planning (APQP).

From the IATF point of view, the requirement that includes PPAP is included in section 8.3.4.4 – Product approval process. One of the important things mentioned in this section is the information regarding completion of the approval process of externally supplied components (often referred to as “Buy components”) prior to submission of the final product.

Recommendation in such case is that the submission of parts should take place after internal or external verification of the manufacturing process directly by the customer representative (SQE, STA ect).

PPAP elements

During the PPAP, the organization must submit 18 elements to the customer, which guarantee that the supplier is able to meet the appropriate quality and quantity requirements for the manufactured product. All of them are listed below:

  • Design Records
  • Engineering Change Documents
  • Customer Engineering Approval
  • Design FMEA
  • Process Flow Diagrams
  • Process FMEA
  • Control Plan
  • Measurement System Analysis Studies MSA
  • Dimensional Results
  • Records of Material / Performance Test Results
  • Initial Process Studies
  • Qualified Laboratory Documentation
  • Appearance Approval Report
  • Sample Production Parts
  • Master Sample
  • Checking Aids
  • Customer Specific Requirements
  • Part Submission Warrant (PSW)

Depending on the submission of parts required level (from 1 to 5) there are two approaches which are used:

  • are submit to the client and in parallel supplier keeps copies of documents and samples in the appropriate place or
  • supplier keeps copies of documents and samples in a suitable place and make them available to the customer upon request

If the submission level is unknown, please contact the customer – the default level is level 3. In addition, customer approval is required before production reflecting the maximum quantities for the production ramp-up curve.

Production parts preparation

Parts for approval must be taken from a significant production run, ie 1 hour to 8 hours and a minimum of 300 consecutive parts, unless otherwise agreed in writing with the customer. Additionally, the production process should be OTOP (off-tool off-process) status, which means that it should be final and should be in a definitive production location.

It is also worth remembering that when submitting parts dedicated to PPAP to the client, we should obtain approval for all sub-components included in the manufactured product.

PPAP – Production Part Approval Process (2024)

FAQs

What is the PPAP production parts approval process? ›

Production Part Approval Process (PPAP) is used in the Aerospace or automotive supply chain for establishing confidence in suppliers and their production processes. Actual measurements are taken from the parts produced and are used to complete the various test sheets of PPAP.

How many samples are required for PPAP? ›

The AIAG SPC and PPAP manuals recommend at least 100 samples. Sometimes collecting samples can be difficult or costly. Either way, using Minitab's confidence intervals you will get a better sense of the variability and avoid costly mistakes that could come as a result of a small sample size.

How long does a PPAP take to complete? ›

The timeline for PPAP can vary widely depending on the complexity of the parts, the level of PPAP required, and the efficiency of communication between suppliers and manufacturers. It can take anywhere from a few weeks to several months.

How do I fill out a PPAP document? ›

Essential in automotive and aerospace industries, manufacturers must accomplish seven documents for PPAP:
  1. Product description.
  2. Samples of the part.
  3. Manufacturing process.
  4. Inspection process.
  5. Quality plan.
  6. Part history.
  7. Supplier approval form.
Dec 13, 2023

What is a PPAP checklist? ›

PPAP (Production Part Approval Process) relies on a framework of documents, customer requirements, and authorizations to ensure that a supplier produces parts reliably and repeatedly. The PPAP Requirements Checklist answers the following questions. Are all required documents complete and approved?

What are PPAP samples? ›

The PPAP manual contains detailed information, guidelines and sample documents useful for completing the process requirements. The resulting PPAP submission provides the evidence that the supplier has met or exceeded the customer's requirements and the process is capable of consistently reproducing quality parts.

Who is responsible for PPAP documents? ›

Each PPAP level determines the specific requirements for each element and indicates which elements should be submitted to the customer. It is important to note, however, that the supplier, regardless of PPAP level, must complete every applicable element no matter what level the PPAP is.

What is a significant production run in PPAP? ›

A significant production run is defined as the following: a continuous eight-hour production run or a minimum of 300 manufactured parts, whichever comes first. This run shall be manufactured at the production site using the tooling, gaging, process, materials, and operators from the production environment.

What are a level 3 PPAP requirements? ›

A Level 3 PPAP requires that you submit all the documentation of a PPAP except elements 15 and 16, which are the master sample and checking aids. InspectionXpert needs the contact information you provide to us to contact you about our products and services. You may unsubscribe from these communications at any time.

Do you charge for PPAP? ›

Some manufacturers charge upwards of $300 or more for each PPAP package.

What is PPAP interim approval? ›

Interim PPAP Approval Forms (PSWs) allow suppliers and customers to approve shipment of parts either for a set period of time and/or for a number of parts. The PPAP Approval Form (PSW) serves to confirm the APQP record's contents and and is used to submit and approve the APQP process as a whole.

What is the lowest level of PPAP? ›

Level 1 is the least rigorous and requires only a part submission warrant (PSW), which is a form that summarizes the PPAP results and certifies that the supplier has met the customer's specifications.

What is the first part approval? ›

Generally, it is the inspection that is done to the first piece that comes off of an assembly line or manufacturing process, AFTER A CHANGE IS MADE. The First Piece Approval goes over the new part and makes sure the new features/shapes are in place and working.

How to do a PPAP audit? ›

The 18 elements of a PPAP submission:
  1. Design Records.
  2. Engineering Change Documents.
  3. Customer Engineering Approval.
  4. Design Failure Mode and Effects Analysis (DFMEA)
  5. Process Flow Diagrams.
  6. Process Failure Mode and Effects Analysis (PFMEA)
  7. Control Plan.
  8. Measurement System Analysis (MSA)

What are the 5 core tools? ›

5 Core Quality Tools are the essentials of a quality management system in manufacturing. 5 Core Quality Tools consist of APQP, PPAP, FMEA, MSA, and SPC. Goal of 5 Core Quality Tools is to prevent errors rather than detect, creating impactful savings.

What is meant by production part approval? ›

Production Part Approval Process (PPAP) is a key procedure within aerospace and automotive manufacturing to ensure that parts manufactured by suppliers are created consistently.

What is the main purpose of the PPAP? ›

The Purpose of the PPAP is to:

Ensure that a supplier can meet a customer's manufacturing and quality requirements for their products. Prove, with objective evidence, that the supplier fulfilled all customer specifications and engineering drawing requirements.

What are the three phases of PPAP? ›

Phased PPAP separates the PPAP process into three phases: Phase 1 is called 'Quality Verification' ❑ Phase 2 is called 'Production Verification' ❑ Phase 3 is called 'Capacity Verification'. Note: For less complex components/commodities/production streams, it is possible to complete multiple phases as a single event.

Top Articles
Latest Posts
Article information

Author: Merrill Bechtelar CPA

Last Updated:

Views: 6321

Rating: 5 / 5 (50 voted)

Reviews: 89% of readers found this page helpful

Author information

Name: Merrill Bechtelar CPA

Birthday: 1996-05-19

Address: Apt. 114 873 White Lodge, Libbyfurt, CA 93006

Phone: +5983010455207

Job: Legacy Representative

Hobby: Blacksmithing, Urban exploration, Sudoku, Slacklining, Creative writing, Community, Letterboxing

Introduction: My name is Merrill Bechtelar CPA, I am a clean, agreeable, glorious, magnificent, witty, enchanting, comfortable person who loves writing and wants to share my knowledge and understanding with you.