Primavera P6 Progress Update in 7 Steps - Proove (2024)

Once your qualitative project baseline is set up, approved and your project has started, the next step is to closely monitor and track the progress of the project. When this is your first time updating a schedule in Primavera P6, this can become quite challenging. There are different crucial settings and pitfalls to be addressed during the updating process.

The procedure for progress updates we use as experts is not by applying the “Update Progress” or “Apply Actuals” functions in P6. These functionalities strongly reduce the control on the schedule.

In the following 7 steps we will guide you through the advised method to add progress to your schedule.

Step 1: Assign a Baseline

In order to track your schedule performance, a baseline is essential as a reference for your project. It would be good practice to safe the current schedule as a baseline before making any changes. When assigning the baseline, you can choose between 2 types:

Project Baseline: This baseline is the official approved project schedule as agreed with the client. The project baseline is a fixed programme that can only be changed through change control. No progress should be contained in this type of schedule.

User Baseline: These are the unofficial baselines that the user can create to measure the performance as the project progresses. Often these are time snapshots of the project, for instance a previous progress update.

Once assigned, the properties of the baselines can be visualized as activity columns and as Gantt chart bars together with the current schedule. This will greatly improve your insight in the schedule performance during and after updating.

Primavera P6 Progress Update in 7 Steps - Proove (1)


There are a few things that can go wrong when assigning a baseline in P6. Some special attention is needed for the following points:

  • Primavera P6 relates the current schedule and the baselines based on the activity ID. Make sure no activity IDs are changed or reused.
  • Be careful when you choose to convert another project as a new baseline, that project will be removed from your EPS. You can choose to restore it back again afterwards.
  • Are your baseline dates and bars not showing correct values? Find a solution to your issue in our blogpost about baseline bars (in the wrong place).

Step 2: Collect Progress Input

Next, progress is collected and entered in the tool. Here, a well-documented input data sheet is the key to success. Collect all the necessary information of the planned activities up to the Cut-Off Date and Hour. Is your progress up to and including Friday? Then your Data Date should be on the Saturday on 00:00.

There are 2 useful tools to visualize the activities that are currently scheduled in the period leading up to the Cut-Off Date:

  • Use the P6 Progress Spotlight function
  • Create a ‘look ahead’ filter where the Remaining Early Start is within a range from the current Data Date and the Cut-Off Date

The required input for these activities will depend on the activity status as depicted in the table below:

Primavera P6 Progress Update in 7 Steps - Proove (2)


Some aspects to consider when collecting the progress input for an update in P6:

  • Make sure actual dates are before the Cut-Off Date
  • The Activity % complete can be based on Duration, Physical or Units % complete. Want to know more about % complete? Check our blogpost!

Step 3: Enter the Progress

The progress from the previous step can now be implemented directly in P6 in the same order as the previous table:

  1. Activity Status
  2. Dates
  3. Physical % complete/Units/Costs/Expenses (if applicable)

At this point your schedule might not look correct; durations and dates don’t seem in line with the input, relationships are not respected, etc…. Don’t worry, this is normal at this stage. Don’t let this freak you out by scheduling too early.

Some aspects to consider while entering the progress in P6:

  • Unlike MS Project, P6 does not recalculate the remaining duration itself based on the new Data Date. The new remaining duration or an expected finish needs to be filled in manually.
  • Is P6 not allowing you to insert a certain actual start or finish date? Check the activity calendar and the time of the dates
  • Resource calculations will depend on the activity Duration Type and the Project Resource Assignments settings under your project calculations. Make sure to check these settings when the resource progress is not acting as desired when adding unit/cost actuals.

Step 4: Schedule Based on New Data Date

Once we have entered all our input, it’s time to press F9 and fill in the new Data Date I.e., the Cut-Off Date. Primavera will reschedule activities after the Data Date based on the Critical Path Method. Before we sit back and relax, carefully check the scheduling options in the schedule window.

A specific scheduling option related to projects in progress, is how P6 should deal with out-of-sequence activities. For out-of-sequence activities you can choose to ‘retain logic’, ‘progress override’ or use ‘actual dates’. In our blogpost "Scheduling progressed activities" we go more into detail about the effect of this function on your schedule.

Primavera P6 Progress Update in 7 Steps - Proove (3)


Activities that are out-of-sequence are reported in the scheduling log file. This file also warns for progress irregularities like activities with actual dates later than the Data Date.

Step 5: Revise Schedule

Make sure to check the scheduled programme thoroughly before proceeding. Verify if the schedule is in line with the input from your data sheet. Make changes if necessary and reschedule.

After this technical check, also perform a sanity check. Are the performed activities making sense and is the impact on the future schedule realistic? Big impacts on the schedule should be explainable.

Step 6: Reporting

Now that all this progress is implemented and processed by the schedule, the data needs to be visualised in useful layouts that facilitates the analysis of the schedule. Output created from the schedules should enable the project manager to have a clear view of the project performance and identify possible planning issues that need some attention.

The possibilities for creating useful progress layouts in P6 are endless. Let’s give some examples:

  • Baseline differences
  • Critical activities
  • Resource S-curves
  • Lookahead Schedule
  • ….
Primavera P6 Progress Update in 7 Steps - Proove (4)


Tip
: P6 has a Progress Line function that visualises which activities are behind schedule (left of Data Date line) and the activities ahead of schedule (right of Data Date line)

Primavera P6 Progress Update in 7 Steps - Proove (5)

Step 7: Analyse

After monitoring, we need to control by analysing and influencing our project. To properly control our project, we need to be critical and learn from our analysis. What are the reasons activities are taking longer? What and how are activities underperforming? Why are activities becoming critical? Use this knowledge to get a better understanding and to have better estimations of the future. By re-evaluating the future schedule based on the gained knowledge during the execution, possible problems can be identified and mitigated at an early stage.

Conclusion

After you successfully completed these 7 steps, your progress update reflects the actual works and forecasts the future works. Based on this progress update, possible issues can be identified and form the basis of a mitigation plan. This schedule change analysis is part of the control phase where the schedule is reassessed and optimised. These mitigation actions will lead to changes in the schedule such as adjustments in resources, logic links, activities, … etc. This procedure is called “half-step scheduling” and can be seen as a non-progress revision based on knowledge gained from the progress reporting.

Do you have some additional knowledge about Progress Updating that you want to share with us? Get involved and let us know in the comment section below!

Primavera P6 Progress Update in 7 Steps - Proove (2024)

FAQs

What is the difference between retained logic & override logic in progress update? ›

Choosing Retained Logic, the remaining duration of an in-progress activity will not be scheduled until all predecessors are completed. Choosing Progress Override, ignores the network logic and the activity progresses without delay. Choosing Actual Dates, forward and backward passes use actual dates.”

What is the difference between apply actual and update progress in P6? ›

The Apply Actuals function will update any activities with the “Auto Compute Actuals” checkbox marked… …whereas the Update Progress (Progress Spotlight) feature will update activities which fall within the spotlighted region regardless the status of “Auto Compute Actuals” checkbox.

How do I update progress in Primavera P6 from Excel? ›

Once the project team has updated the Excel file, to import the updates into Primavera P6, select the File tab, and then select “Import”: Select “Spreadsheet – (XLSX)”, and then select “Next”: Use the ellipsis to find the location of the saved file which contains the updates.

How do you update project progress? ›

On the Project tab, in the Status, group, choose Update Project. In the Update Project dialog box, select Update work as complete through, and then type or select the date through which you want progress updated. Important: If you don't specify a date, Project uses the current or status date.

How do I present my progress update? ›

Focus on the data. Be clear, concise, and stay on topic. Your goal here is to present what is relevant, clearly, as simply and accurately as possible. Present your progress by milestones.

What is the difference between retained logic and progress override in P6? ›

Retained Logic respects the network logic. When scheduling using Progress Override, Primavera P6 ignores the relationship between the activities and schedules any remaining duration of the “out of sequence” activity from the data date.

How do I fix out of sequence activities in Primavera? ›

How to resolve or Fix Filter out of Sequence activities in Excel
  1. In First Case change the relationship status to Start to Start or Finish to Finish.
  2. In Second Case change the relationship status Finish to Finish.
  3. In third Case change the relationship status Start to Start.
Jul 23, 2022

How do I reduce total float in Primavera P6? ›

To remove negative float from summary activities, you'll need to adjust the P6 Schedule Options. This can be opened by selecting Tools > Schedule > Schedule Options. In the Schedule Options window, you can adjust how Total Float is calculated.

What are the different activity status types in Primavera? ›

Primavera P6's 3 Types of Activity Percent Complete

Physical % Complete.

What do you mean by updating of project & why it is essential? ›

(i) The process of reviewing the progress of project execution and redrafting the network according to the latest requirement is called “updating”. (ii) During redrafting, scheduled dates are revised. New critical path may emerge and hence project priorities may change.

What is the difference between planned and actual in Primavera P6? ›

This DD is the point in time between the work that has been accomplished and the work still to be done. Planned progress is measured in Primavera P6 using schedule % complete. Actual progress is specified with performance % complete, a more complex term in Primavera P6 Professional.

How do you automatically update charts when new data is entered? ›

Simply format your source data as a table, then create a chart based on that table. When you add more data below the table, it will automatically be included in both the table and the chart, keeping everything consistent and up to date.

How do you update a chart to include new data? ›

The easiest way is to simply select the new data range you want to use for your chart, and then click on the "Update" button in the "Data Range" section of the Excel Chart Tools ribbon. This will automatically update your chart to use the new data range.

How do you update a chart after changing its source data? ›

Right-click your chart, and then choose Select Data. In the Legend Entries (Series) box, click the series you want to change. Click Edit, make your changes, and click OK. Changes you make may break links to the source data on the worksheet.

How do I ask for a progress update example? ›

What Is the Best Way to Politely Request an Update From Your Client? (With Email Samples)
  1. "Can you please update me?"
  2. "Would it be possible to receive an update?"
  3. "Would you kindly give me an update?"
  4. "Can you please give me a quick update?"
  5. "Just checking in"
  6. "I wanted to see how things were going"
Aug 9, 2022

What is a progress update? ›

Progress updates are your successes, achievements and milestones i.e. things which have moved you forward in the achievement of your objectives.

Who can update the progress status of an action? ›

Any project member can set a status to inform other project members on a project's progress.

What should be included in a progress presentation? ›

Project Progress Report

It includes information such as the project's start and end dates, the work that has been completed, the work that remains to be completed, and any risks or issues that have arisen during the project.

What should a weekly project update include? ›

The Weekly Project Status Report

These types of reports should include as many relevant details as possible, including a detailed view of the progress of the project. It also tracks the budget, indicates milestones, specifies risks, and more.

What do you say in a progress report? ›

A daily progress report includes your goals for the day, as well as your accomplishments the previous day. It also explains challenges encountered in performing tasks and achieving goals. Another section under the daily report is 'lessons learned'.

What is difference between dissolve and delete in P6? ›

Deleting an activity removes the activity and its logic/relationship ties. Dissolving the activity removes the activity but links its predecessor to its successor to maintain schedule logic continuity.

What is out of sequence activities in P6? ›

What is Out-of-Sequence Progress in Primavera P6? Out-of-sequence progress in Primavera P6 occurs from a deviation in the original planned logic that was set up in the baseline schedule. It can occur when work is executed in the field in a different order than was planned in the schedule.

What is retained logic in Primavera P6? ›

Retained Logic: The remaining duration of a progressed activity is not scheduled until all predecessors are complete. It also prevents tasks from “front-loading” since the remainder of the work is held out.

What is one of the major outputs of activity sequencing? ›

Some outputs from activity sequencing include project network schedule diagrams, activity list updates, activity attributes updates, and requested changes.

What is sequence editing? ›

Sequence editing features include changing and deleting bases, reverse complementing, inserting gaps and bases, moving gaps and samples in contigs, undo and redo, deleting samples from contigs, splitting contigs, and changing bases to lower / upper case.

Why is it important to determine activity sequencing on projects? ›

Sequencing tasks is an important part of project task management because it helps you make the most out of your resources and help you identify critical tasks and prioritize them.

How much total float is acceptable? ›

Total Float values are limited to 44 days, therefore review tasks that have greater than 2 months total float and limit their usage to 5% of incomplete tasks. Negative Float – Schedules that have negative float tasks are already behind. Ideally the DCMA says avoid having negative float in your schedule.

Why is my total float so high? ›

High float is a large number of days of float. Tasks with high float have a long period that they can flex within without there being an impact on the critical path. Some tasks might genuinely have that much slack in the schedule. For example, you may need to have a quality meeting at some point next quarter.

Can total float be smaller than Free Float? ›

No, Total Float is not always greater than Free Float. Total Float represents the amount of time that a task can be delayed without affecting the completion date of the project, while Free Float represents the amount of time that a task can be delayed without affecting the start date of its subsequent tasks.

How do you update actual cost in Primavera? ›

If you want the Actual Cost of an activity to update when the activity duration progresses, toggle on the resource assignments calculation setting “recalculate actual units and cost when duration % complete changes.”

How do I change the project actual start date in Primavera P6? ›

Schedule your project start date or finish date
  1. Click Project > Project Information.
  2. In the Schedule from list, pick Project Start Date or Project Finish Date.
  3. In the Start date or Finish date box, enter the date that you want to schedule from.

What is apply actuals in Primavera? ›

Apply an Actual Start to all Activities that have a Planned Start < Data Date. The Actual Start is set to the Planned Start. Level of Efforts and WBS Summary activites get there dates from other activities. Planned Finish is not changed.

How does Primavera calculate progress? ›

Computed as ((Planned Duration - Remain Duration) / Planned Duration) * 100. Always in the range 0 to 100. The planned duration is taken from the current plan, not from the current baseline.

What is the difference between duration complete and physical complete? ›

The duration percent complete type is the simplest to use as the remaining duration is automatically computed by Primavera P6 when the duration percent complete is entered. The physical percent complete type requires the additional step of entering either the remaining duration or expected finish date.

How do you calculate the actual cost of a project? ›

Actual Cost Calculation

Actual material cost = (Number of units of materials) x (Price per unit) Actual labor cost = (Total labor hours used) x (Salary of direct workers per hour)

How do I make the date automatically update in project? ›

In the Schedule group, click the arrow on Mark on Track, and then select Update Tasks. The Update Tasks dialog appears. Under Actual, enter the new dates in the Start and Finish boxes.

How do you change the date range of a project? ›

Set timeline date ranges

Click anywhere on the timeline to open the Timeline tab, then in the Show/Hide group click Set Date Range. On the Set Timeline Dates box, select Set custom dates, fill in your desired start and finish dates, and then click OK.

What is auto complete actuals? ›

Auto compute actuals calculates actuals for your selected activities within a data date period depending on their “% complete type”. The schedule would essentially reflect progress as planned (no further changes or delays to what you have currently).

What is actual units in Primavera P6? ›

Actual units is the sum of the labor units and nonlabor units, and remaining units is equal to the sum of the remaining labor units and remaining nonlabor units. It simply shows that how much of the units are actualized so far.

How do you assign a baseline in P6? ›

Assigning Baselines

Once your baselines have been defined, you can assign them to the four baseline slots in Primavera P6. To do this: Go to Project > Assign Baselines: On the Assign Baselines screen, you will see four dropdowns for the Project Baseline, followed by Primary, Secondary, and Tertiary.

How to compare 2 schedules in P6? ›

To access the Schedule Comparison tool, select Tools > Schedule Comparison. This will automatically open up the P6 Visualizer in another window. The Primavera P6 Visualizer is a reporting-tool within P6 that allows you to create customizable Gantt charts and Timescale Logic Diagrams.

What is claim digger in P6? ›

Claimdigger is actually its own separate product that has been built in to P6. It is an application that compares two project plans, a revised project and a baseline projects, and creates a report on the differences between the project plans including: Items changed. Items deleted. Changed Values.

What is planned vs actual called? ›

And plan vs. actual analysis, also called variance analysis, is essential to better business management. That's where you track results, review progress, and make regular course corrections depending on performance.

Top Articles
Latest Posts
Article information

Author: Dr. Pierre Goyette

Last Updated:

Views: 6681

Rating: 5 / 5 (50 voted)

Reviews: 81% of readers found this page helpful

Author information

Name: Dr. Pierre Goyette

Birthday: 1998-01-29

Address: Apt. 611 3357 Yong Plain, West Audra, IL 70053

Phone: +5819954278378

Job: Construction Director

Hobby: Embroidery, Creative writing, Shopping, Driving, Stand-up comedy, Coffee roasting, Scrapbooking

Introduction: My name is Dr. Pierre Goyette, I am a enchanting, powerful, jolly, rich, graceful, colorful, zany person who loves writing and wants to share my knowledge and understanding with you.