First, some of these terms are "work activities" (or "a work process") and some are the "deliverables" (or the "product") of a work activity. Lets start by putting them in the order we would normally see accomplish them.
Plant layout: This is first a "work activity." It is the process of determining what Area you have for a Plant, the equipment or units you need to fit into the Area and the exact relationship these items must have relative to each other. In the past it has been done with manual sketches, paper cut-outs and small scale block models. Today it can be done in "Model Space" by moving around circles, rectangles and squares, as long as you keep it simple. Remember, this is an activity, it is not a deliverable. You can call it the Plant Layout, but it is still not the deliverable.
Plot Plan: (aka: General Arrangement drawing or GA): This is a "deliverable." After the overall plant layout or unit layout has reached a point where the actual equipment number, sizes and shapes are known the "Model Space" version of the plant layout can be up-dated and formalized. It would then be moved to "Paper Space", a Title Block added and the formal Plot Plan produced. This document now goes to various people for review and approval including the Client. Because of the timing, the scale and the purpose of this Plot Plan document it would not and should not have any coordinates or dimensions on it to locate equipment or facilities.
Location Control Plan (LCP): This document is a limited internal deliverable tool that would not and should not be issued to the job site. This is the more detailed step to fixing the location of each piece of equipment in to its final location. This final location will be based on the purpose, function size of that piece of equipment along with the piping layout, operation space and the maintenance space. In addition to this there are the space requirements for any related electrical equipment and instrumentation requirements. The final location of each piece of equipment is also affected by the foundation design, and the foundation design is impacted by the type and stability of the soil at the site. The final location of a piece of equipment should only be conveyed to the field by the document (maybe called Foundation Location Plan) from the Structural department.
Piping Layout: This is first an activity (or a process) and then a product. A piping designer does piping layout. This is the process of defining the piece of equipment, the maintenance spaces and the related electrical needs. Then routes the piping to accomplish the process function of the piece of equipment then add the space requirements for operation and you have a piping layout. The final location of any piece of equipment is impacted by the piping layout. This final location is added to the "GA" (or LCP) which is then routed to the structural group. As you can see there is a normal understood cycle and recycle between the piping group with the piping layouts, the "GA's" and the structural group and their "Foundation Location Plan".
Piping Plans (& Sections): These are the most detailed drawings created by the Piping Engineering and Design effort.They may be created via 2D CAD or be extracted from a 3D model. The level of detail is very specific. The equipment is shown in rough outline but with Equipment Number, key centerline coordinates all the nozzles.The nozzles are all shown in detail and in exact location and identification. Piping is also shown in detail with enough information to draw or check Isometrics.
Check online plant engineering courses at www.iniped.com
Help improve contributions
Mark contributions as unhelpful if you find them irrelevant or not valuable to the article. This feedback is private to you and won’t be shared publicly.
Contribution hidden for you
This feedback is never shared publicly, we’ll use it to show better contributions to everyone.
Like
Celebrate
Support
Love
Insightful
Funny
193
6 Comments
Mohammed Kamal Gaber
Sr.Process Engineer , Petrojet - Ph.D.
4y
- Report this comment
GA drawings are not the same as layout , they are dedicated to certain equipment area .These drawings are very helpful to site fabrication works, and it shows supports locationz and types in a quiet detailed way and of course refers to pipe support detail drawings.Thank you.
2Reactions 3Reactions
Funke Taylor PMP
Energy Professional | C-suite Executive | Process Engineer | Digital transformation enthusiast | Founder @The Energy Axis
4y
- Report this comment
Lol @ 'go for tea breaks'. I can relate. I know that line too well...its so convenient to blame you (as the Process Lead) for why other disciplines are not putting out thier deliverables.
1Reaction 2Reactions
Vijay Sarathy
4y
- Report this comment
The plot plan is equally important for process engineers at basic/pre-feed stage to make preliminary estimates. Since piping designers take some time to prepare the piping layout, process engineers use the plot plan for example to arrive at a preliminary pipe/pipeline sizes & associated pressure drops, equipment capacities, etc. Such documents will have lot of "Holds", marked in the reports & issued internally as 'rev0' documents.On a lighter note, those rev0 documents are important for process engineers to save themselves from other department's complaints like - "Sir, these process fellows didn't issue the process design basis, so we are going for tea breaks"!! 😄😄😄
4Reactions 5Reactions
Dr. Javier Blasco Alberto
Associate Professor at School of Engineering and Architecture (Univ. Zaragoza)
4y
- Report this comment
Thanks to James O. Pennock for providing us the texts for this article
1Reaction
See more comments
To view or add a comment, sign in
More articles by this author
No more previous content
- What are some common types of heating or cooling jackets or coils for jacketed pressure vessels? Jan 13, 2020
- 10 reasons to use pipe class software vs spreadsheets Nov 6, 2019
- Why does a piping branch connection not break when the operation pressure rises above the design pressure? Oct 30, 2019
- What is the difference between required, nominal and analysis pipe wall thickness? Sep 16, 2019
- Selection of pumps following API-610, ISO-13709 Sep 10, 2019
- Feedforward control in centrifugal compressors Sep 4, 2019
- Acoustic Induced Vibration (AIV) in Piping System Jun 20, 2019
- Good Rotordynamics Performance for Industrial Rotating Machinery Jun 18, 2019
- Effect of pipe pressure on flange bolt-loading Jun 14, 2019
- Interaction between the compressor impellers geometry and the process thermodynamic Jun 11, 2019
No more next content
Sign in
Stay updated on your professional world
Sign in
By clicking Continue, you agree to LinkedIn’s User Agreement, Privacy Policy, and Cookie Policy.
New to LinkedIn? Join now
Insights from the community
- Structural Engineering What are the advantages and disadvantages of using bolted or welded connections in structural steel design?
- Structural Engineering What are the best practices for designing reinforced concrete structures with STAAD Pro?
- Steel Design How do you ensure adequate shear connection between steel and concrete in composite sections?
- Steel Design What are the main differences between Eurocode 4 and AISC 360 for composite design?
- Structural Engineering What design codes and standards are essential for reinforced concrete design?
- Construction Management How can you reduce costs when using STAAD in construction projects?
- Construction Drawings What are the advantages and disadvantages of using different units and formats for dimensions?
Others also viewed
- Static and Dynamic Analysis of Piping Systems on FPSO Topside Modules Peter TAO 8y
- GENERAL ARRANGEMENT DRAWINGS ENECA GROUP OF COMPANIES 8mo
- General Arrangement Drawings ENECA GmbH 1y
- Plot Plan Optimization Nish*t K. 5mo
- What is a Plot Plan? Saleh AlOtaibi 1mo
- Here Are All The Key Facts To Know About Piping Expansion Loops Nathan Taylor 1y
- MECHANICAL ISOLATION PHILOSOPHY Shashidhar Bhat 2y
Explore topics
- Sales
- Marketing
- Business Administration
- HR Management
- Content Management
- Engineering
- Soft Skills
- See All